Installing and Configuring the Director
59
Director 2/64 Installation Guide
Prepare the Front and Rear Rack Columns
Use the following procedure to prepare the rack for installing a switch:
1. Prepare the front rack columns, as shown in
a.
Standing at the front of the rack, count up from the top of the rail tray (
1
)
to the 13th, 19th, and 23rd holes on the rack's front face.
b.
Slide a sheet metal nut (
2
) on each of the located holes.
Note:
Three sheet metal nuts should be on each front column face (
3
).
Figure 21: Preparing the front rack columns
2. Prepare the rear rack columns, as shown in
:
a.
Standing at the back of the rack, count up from the top of the rail tray (
1
)
to 12th and 28th on the rack’s back face.
b.
Slide a sheet metal nut (
2
) on each of the located holes.