Installing and Configuring the Director
109
Director 2/64 Installation Guide
Connecting Cables to the Fibre Channel Ports
Use these steps to connect Fibre Channel port cables:
1. Route the fiber-optic cables from customer-specified devices to ports at the
front of the director, as shown in
.
.
Figure 59: Connect the Fibre Channel cables
2. Connect device cables to ports and route the cables through the cable
management assembly at the bottom front of the director. Start with the center
UPM cards (cards 7 and 8) adjacent to the CTP2 cards and work outward. In
addition, start with the bottom port of each UPM card and work upward.
3. Bundle Fibre Channel cables from the director and other equipment (groups
of 16 maximum) and secure them as directed by the customer.
4. Set the director online. For instructions, see “
” on
1
Director 2/64
2
Fibre Channel cables
3
Workstation