Airflow Optimization kit
Kit overview
The Airflow Optimization kit enables you to install foam rail gaskets in your 36U, 42U, and 48U 600-mm (24-in) wide racks
and 48U 800-mm (31-in) wide racks to improve separation between hot and cold aisles in the data center.
Kit contents (BW930A)
Item
Quantity
Foam rail gasket roll
4
600-mm (24-in) perforated floor gasket
—or—
800-mm (31-in) perforated floor gasket
1
Extra hardware might be included for your convenience.
Required tools (airflow optimization kit)
The following tools are required for installation:
Knife or scissors
Installing foam rail gaskets between racks
Procedure
1. Cut the foam rail gasket to fit the size of your rack.
2. Insert the foam rail gasket between the racks. Ensure that the closed cell side of the gasket faces the front of the rack.
Airflow Optimization kit
11
Summary of Contents for G2 Series
Page 16: ...Ballast kit 16 ...
Page 19: ...5 Re attach the front and rear doors Baying kits 19 ...
Page 26: ...Cable Management Combo kit 26 ...
Page 29: ...Rack Roof Mount Fan kit 29 ...
Page 42: ...Hook and Loop Cabling Strap Clip kit 42 ...
Page 43: ...Hook and Loop Cabling Strap Clip kit 43 ...
Page 45: ...4 Bundle rack cables as required 1 4 Turn Hook and Loop Cabling Strap kit 45 ...
Page 57: ...Server Utility Shelf kit 57 ...
Page 65: ...Side Panel kit 65 ...
Page 68: ...5 Tighten the bolts from steps 2 and 4 Stabilizer kit 68 ...