Air distributor
For this purpose adjust the valves on both sides
evenly to apply more fan air to the desired
hopper.
After sowing reset the valves again.
0
0
Air distributor with valves
The correct distribution must be determined by
field tests or using a test placement and should
be checked when starting and during work.
NOTE
¾
Adjust the ventilation flap before starting
sowing.
¾
Always adjust both valves evenly.
¾
Check the settings daily.
The mark above the 0 shows the position of
the valve.
In the middle position 0 the air is distributed
evenly to all hoses.
If the valves are placed more toward the out-
side, more air will enter the inside hoses and
vice versa.
¾
Move the valves back to the middle position
after drilling.
¾
Check the hose assembly and allocation of
the hoppers to the distributor towers before
filling to avoid mix-ups.
Determine fan speed and valve position
For the first drilling incidents or a new seed/
fertiliser combination it is recommended to run
a test placement before starting drilling. This is
necessary to determine the required fan speed,
to achieve correct transverse distribution.
The simulation speed is used to place the de-
sired amount of seed and fertiliser on a level
surface.
¾
Follow the operating instructions of the
E-Manager to this end.
The work signal can be switched via additional
clips in the height adjustment, or by disconnect-
ing the plug from the pressure sensor.
Several test placements with different fan
speeds and ventilation flap settings may prob
-
ably be necessary.
For an accurate evaluation of the results it is
recommended to catch and weigh the quantities
at the individual coulters.