ASSEMBLY AND ANCHORING
6-17
MSHF • 7295-026A
6.5
Anchoring the mast
If work must be stopped, always
complete the current phase
before stopping. Tighten all the
bolts for the latest fixture and
secure the main switch so that
the mast climbing work platform
cannot be operated.
Before starting to fix any
anchors, ensure that the chassis/
ground frame is level.
The wall must be of such a
quality that it can accept the
forces applied to it via the
anchors.
The platform extensions and the
anchors must not come into
contact during raising and
lowering.
The anchor forces must be
approved by the owner or the
person responsible for the
building to which the machine will
be anchored.
1.
Check that the mast is vertical with a
spirit level at least 1 metre / 40 inch
long. Recheck as each anchor is
secured.
2.
The mast must be anchored to the
building at the distances specified in
the table in chapter 1.
3.
The anchors are assembled from
mast adapters, horizontal anchor
tubes and a support tube.
Summary of Contents for MSHF
Page 4: ...IV MSHF 7295 026A...
Page 10: ...X MSHF 7295 026A Fig 1 Dimensions...
Page 14: ...TECHNICAL DETAILS 1 4 MSHF 7295 026A Fig 1 6 Drive unit...
Page 16: ...TECHNICAL DETAILS 1 6 MSHF 7295 026A Fig 1 7 Chassis Fig 1 8 Ground frame...
Page 30: ...SAFETY 3 4 MSHF 7295 026A...
Page 70: ...DISASSEMBLY AND TRANSPORT 8 4 MSHF 7295 026A...
Page 80: ...MACHINE DISPOSAL 11 2 MSHF 7295 026A...
Page 83: ...APPENDICES 1 MSHF 7295 026A...
Page 84: ...APPENDICES 2 MSHF 7295 026A...