36
Heatilator • ECLIPSE-32, ECLIPSE-36 Installation Manual • 2297-984 Rev. B • 6/15
F. Vertical Termination Requirements
Install Metal Roof Flashing
• See minimum vent heights for various pitched roofs
(Figure 7.12) to determine the length of pipe to extend
through the roof.
• Slide the roof
fl
ashing over the pipe sections extending
through the roof as shown in Figure 7.13.
Roof Pitch H (Min.) Ft.
Flat to 6/12........................................1.0*
Over 6/12 to 7/12 ............................1.25*
Over 7/12 to 8/12 ..............................1.5*
Over 8/12 to 9/12 ..............................2.0*
Over 9/12 to 10/12 ............................2.5*
Over 10/12 to 11/12 ......................... 3.25
Over 11/12 to 12/12 ........................... 4.0
Over 12/12 to 14/12 ........................... 5.0
Over 14/12 to 16/12 ........................... 6.0
Over 16/12 to 18/12 ........................... 7.0
Over 18/12 to 20/12 ........................... 7.5
Over 20/12 to 21/12 ........................... 8.0
* 3 foot minimum in snow regions
Figure 7.12 Minimum Height From Roof To Lowest Discharge
Opening
HORIZONTAL
OVERHANG
VERTICAL
WALL
GAS DIRECT VENT
TERMINATION CAP
12
X
ROOF PITCH
IS X/ 12
LOWEST
DISCHARGE
OPENING
2 FT.
MIN.
20 INCHES MIN.
H (MIN.) - MINIMUM HEIGHT FROM ROOF
TO LOWEST DISCHARGE OPENING
NOTICE:
Failure to properly caulk the roof
fl
ashing and
pipe seams could permit entry of water.
• Caulk the gap between the roof
fl
ashing and the outside
diameter of the pipe.
• Caulk the perimeter of the
fl
ashing where it contacts the
roof surface. See Figure 7.13.
• Caulk the overlap seam of any exposed pipe sections
that are located above the roof line.
CAULK
Figure 7.13
Figure 7.13
Figure 7.14 insert Bolt into Brackets
Figure 7.14 insert Bolt into Brackets
Assemble and Install Storm Collar
CAUTION! Risk of Cuts, Abrasions or Flying Debris.
Wear protective gloves and safety glasses during instal-
lation. Sheet metal edges are sharp.
• Slide the storm collar onto the exposed pipe section
and align brackets.
• Insert a bolt (provided) through the brackets and install
nut. Do not completely tighten.
• Slide the assembled storm collar down the pipe section
until it rests on the roof
fl
ashing (see Figure 7.14).
• Tighten nut and make sure the collar is tight against the
pipe section.
• Caulk around the top of the storm collar. See Figure 7.15.