Q-Drive Installation, Operation, and Maintenance Manual
35 of 59
8. Torque the tie rods to 200 ft lbs (271 Nm). Follow the tightening pattern on the label.
Afterwards, be sure to position leveling screw back to starting position. Typical to count and record
rotations when tightening. Use the recorded values from disassembling procedure.
9. Check all the flow directions on the check valves to identify the Inlet and Outlet Check Valves.
10. Check all connections to prepare to start.
Checklist for Inspection and Preventative Maintenance
Haskel Q Drive
Safety Inspection and Preventative Maintenance
Serial Number:
Performed By:
Date:
1. Inspection – Lockout Power! Risk of Electrical Shock!
Pass
Fail
1.1
External surfaces is free of damage and secure.
1.2
Control panel is free of damage and legible.
1.3
All labels are legible and secure.
1.4
Power switch is functional and secure.
1.5
Vents are free of damage and unobstructed.
1.6
Connections are tight and straight.
2. Gas Sections
Pass
Fail
2.1
Barrel
2.2
Piston
2.3
Piston seal
2.4
Check Valves
2.5
Tie Rods
2.6
Leveling
3. Servo Actuator
Pass
Fail
3.1
Oil level is visible.
Comments
Summary of Contents for Q-Drive QGD Series
Page 1: ...88544_A Q Drive Installation Operation and Maintenance Manual Model QGD and QGT ...
Page 57: ...Q Drive Installation Operation and Maintenance Manual 51 of 59 Points of Connections ...
Page 58: ...Q Drive Installation Operation and Maintenance Manual 52 of 59 ...
Page 59: ...Q Drive Installation Operation and Maintenance Manual 53 of 59 ...
Page 60: ...Q Drive Installation Operation and Maintenance Manual 54 of 59 ...
Page 61: ...Q Drive Installation Operation and Maintenance Manual 55 of 59 ...
Page 62: ...Q Drive Installation Operation and Maintenance Manual 56 of 59 ...