Permanent power can be installed at various points
in the overall installation process; however, it must
be installed by a qualified electrical contractor in
compliance with local codes and regulations. The
VPL must be wired to a dedicated circuit, connected
through a 2-pole fused and lockable disconnect,
providing a 120V AC power supply (15 Amp breaker).
The fuses should be a minimum of 15A.
See Figure 4-18
OUTSIDE TOWER
CONDUIT
DPST FUSED DISCONNECT
G
G
N
L
S/L
INSIDE TOWER
JUNCTION BOX
5X WIRE NUTS
Figure 4-18
Route wiring from disconnect to tower as directly
as possible and enter the tower through most
convenient knock-out in the tower side panels.
Inside the tower enclosure, route wires from
knockout to internal junction box along the back
panel of the enclosure. Use the backside of the wire
channel if the junction box is at a different level
than knockout. Be sure all wiring is routed clear of
the moving carriage and roller wheels inside the
tower. See Figure 4-19.
Knockout
Wire Channel
Junction Box
Figure 4-19