HIGHLANDER II VERTICAL PLATFORM LIFTS:
Install Manual
17FEB2021 | 630-00113 REV C
18
INSTALLATION
HIGHLANDER II: SECTION 4
SETTING THE UPPER LIMIT
SWITCH
Typically only the upper limit switch will need to be
adjusted.
Raise the platform so it is level with the upper
landing.
Loosen the bolts on the upper limit switch assembly.
Slide the assembly down until the switch makes
contact with the carriage and makes a clicking
sound. Re-tighten the bolts. See Figure 4-14.
Figure 4-14
CALL STATIONS
Check your state and local codes (ASME A18.1) for
mounting height locations for the call stations.
Call stations can be mounted on a surface or flush-
mounted on a 2-gang outlet box.
1. Remove four (4) label plate screws and label
plate. See Figure 4-15.
Back
Cover
Front
Cover
(4) Cover
Screws
Label Plate
Key Lock
(optional)
Figure 4-15
2. Remove four (4) cover screws and the front
cover from the back cover.
3. Landing wires are pre-wired to the control
board as shown in Figure 4-7. Retrieve
wires that are coiled up inside the tower
and determine the routing of wires going
to the call station. Verify applicable code
requirements.
4. If using the back cover for a wall mount setup,
cut out the desired knock-out for wire routing.
There are four (4) knockouts on the back
cover. Two (2) on the back surface, one (1) on
the top and one (1) on the bottom.
5. If using a flush-mounted setup the back cover
can be discarded.
6. Mount back cover to the wall using
appropriate fasteners through four (4) holes in
the back surface of the back cover.