![background image](http://html1.mh-extra.com/html/hagie/2101/2101_operators-manual-supplement_3196471023.webp)
20
III.
PREPARING TO OPERATE
1. Install
Tasseltrol
®
/LS sensor arm weldment
with the two nylon washers in the bottom
hole in the tool bar (fig. 3.25, item 2).
2. Install the Tasseltrol
®
/LS cross tube weld-
ment (fig. 3.25, item 3) to the sensor arm.
3. Install the left and right slide mount weld-
ments (fig. 3.25, item 4) to the cross tube
weldment.
4. Install the Tasseltrol
®
/LS reflector mount
(fig. 3.25, item 5) and sensor mount (fig.
3.25, item 6) to the slide mount weld-
ments.
5. Install the cable assembly according to the
wire diagram in your HAGIE 2101
SPRAYER/DETASSELER Parts Manual.
6. With a tape measure, set the center of the
top Tasseltrol
®
sensor to a depth of seven
inches (fig. 3.26). Set the top edge of re-
flector to three inches (fig. 3.26).
7. Turn the ignition key switch to the “ON”
position to check the sensor installation.
DO NOT start the engine. See page 39 for
more information about the LS sensor as-
sembly.
ATTACHING LS SYSTEM
FIG 3.26
7”
LS REFLECTOR
LS SENSOR
3”
ATTACHING EQUIPMENT CONTINUED
FIG 3.25
1
4
6
4
5
3
2