12
Figure 9 CR16010E-F chassis depth
NOTE:
•
If the rack does not meet the requirements described in
, the rack door might fail to be
closed after you install the router of standard configurations in the rack.
•
The signal cables and power cords are routed through the front of the chassis. If you use power
cords that has a conductor cross-section area of a minimum of 16 sq mm (0.02 sq in), leave more
space between the front rack posts and the front door as appropriate.
Tools and equipment
No installation tools and equipment are provided with the router. Prepare installation tools and
equipment yourself as required.
lists the tools and equipment that you might use during
installation.
Table 6 Tools and equipment list
Category
Tool
Measuring and marking tools
Long tape
Ruler (1 meter, or 3.28 ft)
Gradienter
Marker
Chalk line
Pencil
Summary of Contents for CR16000-F
Page 40: ...9 Figure 11 Securing the power cord method one Figure 12 Securing the power cord method two...
Page 47: ...16 Figure 22 Installing an SMB coaxial clock cable...
Page 66: ...5 Figure 5 Removing a common card Figure 6 Removing a card with a locking clip 1 3 2...
Page 76: ...15 Figure 19 Replacing an SMB coaxial clock cable...
Page 89: ...12 Figure 14 Example of a device label...