GST200-2 Intelligent Fire Alarm Control Panel
Installation and Operation Manual
Page 16
Wiring Holes
Installation Holes
Fig. 4-1
4.3 Start-up Check
After installation, apply power to it as shown in Fig. 4-2. Turn on the main and standby
power supply in the cabinet and check if the FACP can self-test. The procedures are as
follows.
Check if the digital displays showing time are illuminated one by one.
Check if the LCD showing system messages such as fire alarm is illuminated.
Check if the LEDs showing the state of system can be illuminated one by one.
Check if the LEDs showing the device state on ZCP are illuminated in turn.
Check if the speaker can give loud alarm sounds.
4.4 Connections of Peripheral Devices
4.4.1 Connection of Mains Power
GST200-2 Fire Alarm Control Panel receives power from a 220V/230VAC,
50Hz/60Hz supply. The current flows through a filter to the transformer. The
transformer converts the input mains voltage to 27VAC.
The incoming power feed cable Earth (Green/Yellow) wire should be connected to
the earth terminal.
Connect the live wire to the L terminal and connect the neutral wire to the N
terminal.
Note:
1
)
Do not power the system until the installation is completed.
2
)
The incoming mains cabling to the FACP should be supplied via a switch to
facilitate servicing.