4 Replacement of Parts
2861
SECURING
SCREW (4)
BOILER
MOUNTING
FRAME SCREW (2)
AIR BOX
Diagram 4.25
CLAMPING SCREW (3)
Diagram 4.26
UNION NUT
CONNECTION AND
SEALING WASHER
AIR DUCT
SECURING
SCREW (2)
2860
AIR PRESSURE
SWITCH
5276
CLEAR
RED
ELECTRICAL
CONNECTORS
AIR PRESSURE
SWITCH TUBES
4.28 Expansion Vessel
Renewal of the expansion vessel requires the boiler to be
removed from the wall. As an alternative, a separate expansion
vessel of the same specification may be connected as close as
possible to the boiler, leaving the original in position, refer to
Section 4 in the Installation Instructions.
Release the water pressure and drain the central heating and
domestic water circuits, refer to Section 1.3 and 1.6.
Remove the air box access plate, refer to Installation Instructions.
Remove the fan from the flue collector, refer to Section 4.1.
Remove the air box, secured to the boiler with four screws and
to the air duct with two screws, see diagram 4.24.
Disconnect the boiler water connection union nuts at the front of
the isolating valves, see diagram 1.1.
Disconnect the gas service cock union.
Disconnect the safety valve discharge pipe from the boiler, see
diagram 4.18.
Separate the two parts of the boiler multi-pole electrical connector.
Slacken the clips of the gas service cock and the water isolating
valves.
Remove the boiler from the mounting frame, secured with two
screws at the top, see diagram 4.24. Pull the boiler from the
isolating valve. Unhook the boiler at the top and lift off.
Carefully lay the boiler down on its side for access to the
expansion vessel.
Disconnect the union nut connection, see diagram 4.25 and
discard the sealing washer.
Remove the expansion vessel, secured with three clamping
screws.
Connect the union nut, when fitting the expansion vessel, before
clamping it.