10
I N S TA L L AT I O N , O P ER AT I O N S A N D M A I N T EN A N C E M A N UA L
Forklifts
When using a forklift to raise the line-up to position
rollers underneath, proceed as follows:
1. Expand forklift tines to their maximum
(widest) extension.
2. Carefully insert tines of forklift below one side of
the switchgear line-up at the approximate center
of the panel as shown in Figure 09.
Notice:
Do not attempt to lift or
move the equipment with a forklift
positioned in the front or rear of the
equipment.
3. Raise equipment and position one roller under
the skids close to the raised end of the line-up.
4. Carefully lower the gear until it rests on the roller
as shown in Figure 10.
5. Repeat the lifting process at the other end and
place the appropriate number of rollers under
the skids spacing them evenly across the width
of the line-up.
Spreaders and
timber not
furnished with
equipment
Front
Timber
—
09
—
08
—
10
—
Front view
—
08
Recommended method
of lifting outdoor
enclosure (using
cable spreaders)
—
09
Placing forklift tines
under equipment
shipping skid
—
10
Placement of rollers
under shipping skid
—
Side view
DANGER
WARNING
CAUTION
NOTICE