Start-up and Test
MDE-4339 9820Q ASTRA Installation/Operation • July 2004
36
6. Start-Up and Test
Installation Completion Checklist
Review the information below to verify the proper installation of the Series 9820Q dispensing unit.
If the installation does not meet criteria listed, correct the problem before the start-up is
performed.
1.
To avoid damage to the CPU PC board, verify that the SLOW FLOW
and
FAST FLOW
wires are not shorted to any conduit or chassis metal, mis-wired, or connected to any
equipment requiring more than stated maximum allowable current.
2.
The register and pumping unit must be properly secured.
3.
All plumbing must be complete and tight.
All liquid-carrying lines must be checked for
leaks
.
4.
When DC pulse output lines are used in the pump for connecting to GASBOY fuel
management systems, the AC and DC wires must not share any conduits, junction boxes, or
troughs except as noted in Section 4,
Wire Size
.
5.
All conduit work must be complete. All junction box covers must be secured. Conduits
should not be sealed until the wiring is verified through proper operation.
6.
The unit must be properly grounded.
7.
Before any testing begins, remove any water in the tank through a fill opening, using a suitable
pump. Do not use the GASBOY pump to remove water. Serious damage may occur.
8.
A sufficient volume of fuel must be put in the tank to insure that the liquid level is above the
bottom of the suction pipe.
Summary of Contents for 9822Q
Page 1: ...Series 9820Q ASTRA Installation Operation Manual MDE 4339 formerly 035090...
Page 18: ...GASBOY Series 9820Q 12 MDE 4339 9820Q ASTRA Installation Operation July 2004...
Page 22: ...GASBOY Series 9820Q 16 MDE 4339 9820Q ASTRA Installation Operation July 2004...
Page 32: ...GASBOY Series 9820Q 26 MDE 4339 9820Q ASTRA Installation Operation July 2004...