8. Press the test button (A) on the charging unit for
approximately 1 sec, but not more than 5 sec.!
Make sure that the all-pole circuit breaker is
triggered.
9. Reset the all-pole circuit breaker. Refer to
a reset after a minor ground fault, page 80
.
10. Do a test of the earth faults (AC and DC) with a test
instrument.
11. If necessary, reset the all-pole circuit breaker. Refer
to
6.5 To do a reset after a minor ground fault,
.
12. Set the charging station to state A.
13. Disconnect the test equipment.
14. Test charging an EV.
4.12.16 TO MOUNT THE FRONT COVER OF THE
CHARGING UNIT
1. Mount the front cover of the charging unit.
2. Lock the front cover at the bottom of the charging
unit. Key can only be removed in locked position.
A
B
38
Summary of Contents for ENTITY PRO
Page 1: ...GAROEntityProinstallationand operation GARO Entity Pro installation and operation...
Page 4: ......
Page 8: ......
Page 10: ......
Page 74: ......
Page 84: ......
Page 90: ......
Page 91: ...EC DECLARATION OF CONFORMITY 91 EC Declaration of conformity...