![background image](http://html1.mh-extra.com/html/gardner-denver/airsmart-g2/airsmart-g2_operating-and-service-manual_3568235019.webp)
13-25-606 Page 17
2-6
Electrical Wire Sizing -
A certified electrician familiar with National Electric Codes and applicable local
codes shall size the electrical power wires serving the compressor package. Refer to Fig 2-4 for a
summary of maximum package current draw values.
Package Power
Voltage
Max Current Draw - amps
25 / 20 / 15
575
26.9 / 22.2 / 16.9
"
460
33.7 / 27.8 / 21.3
"
230
67.2 / 55.5 / 42.3
"
208
76.5 / 63.5 / 48.9
Figure 2-4 – Electrical Wiring Sizing Data
GROUNDING
- Equipment must be grounded in accordance with Section 250 of the National Electrical
Code.
Failure to properly ground the compressor package could result in injury or
death. Install ground wiring in accordance with the National Electrical Code
and any applicable local codes.
MOTOR LUBRICATION
- The Hebei type H160-2 motors used with this compressor package have
sealed bearings which have been greased at the factory and require no re-greasing during their
operational life. These motors do not have injection or drain ports for re-greasing.
Summary of Contents for AirSmart G2
Page 2: ......
Page 30: ...4 6 13 25 606 Page 28 300UCC546 C Ref Drawing Page 2 of 3...
Page 31: ...13 25 606 Page 29 4 7 300UCC546 C Ref Drawing Page 3 of 3...
Page 33: ...13 25 606 Page 31 4 9 303UCC546 D Ref Drawing Page 2 of 3...
Page 34: ...13 25 606 Page 32 4 10 303UCC546 D Ref Drawing Page 3 of 3...
Page 69: ...NOTES...
Page 70: ...NOTES...
Page 71: ...NOTES...