To set-up the system, follow these steps:
1. Connect the PLB Antennas or the 4-field G2 Antennas (B) together by using
the pre-installed connection cables of the antennas (E).
2. Plug-in the cable of the BENZING M1 Power Supply Unit at the DB-9 plug of
the M1 Fancier Cable (G).
3. Connect the supplied M1 Fancier Cable (C) to the first PLB or G2 Antenna.
4. Connect the power supply to mains. The green LED "Power Supply" (G) on the
DB-9 plug will light up and the BENZING M1 will start-up.
5. Connect the BENZING M1 (A) to the M1 Fancier Cable.