© Galvin Engineering Pty Ltd
Product Installation Guidelines
Version 1, 19 October 2022, Page
6
of
25
IMPORTANT: Galvin Specialised products must be installed in accordance with these installation instructions
and in accordance with AS/NZS 3500, the PCA and your local regulatory requirements. Water and/or electrical
supply conditions must also comply to the applicable national and/or state standards. Failing to comply with
these provisions shall void the product warranty and may affect the performance of the product.
1. Fit box and connect with mains
−
Create an opening on the left or right side
of the box. Push the transformer cable
through the supplied grommet and leave
around 150mm of free cable inside the box.
−
Using suitable fittings, attach the box inside
the wall. Box must be leveled and installed
parallel to the finished wall.
−
Connect supplied inlets to the thermostatic
mixer and then with mains. Attach the
middle section of the box.
−
Attach one part of the supplied 3M Dual
Lock fastener on the relay unit, and the
other one in the most covenient spot of the
box. Recommended position shown on the
picture above. Align both sides of the
fastener and press the relay unit to fix it on
the box.
−
Check if the isolating valves are in the
‘C O E’ p s t n
Note:
Avoid using heat for soldering near the mixer box and
inlets.
2. Preparation for wall finishing
−
Fix installation cover to protect the mixer
against dust.
−
Leave cover attached until wall is
finished.
Installation cover
Middle section of box
Transformer cable
Sensor connection
cable
Temperature Sensor
replay unit