20
SPARC Enterprise T1000 Server Installation Guide • April 2007
2. Raise the server and insert the ends of the mounting brackets into the left and
right slide rails (
FIGURE 2-8
Mounting the Chassis on the Slide Rails
3. Slide the chassis into the rack.
Caution –
Before continuing, verify that the server is securely mounted in the rack,
and that the slide rails are locked in the mounting brackets.
▼
To Install the Cable Management Bracket
1. Place the cable management bracket across the slide rail assemblies behind the
system chassis.
2. Press down on each end of the cable management bracket until the ends click into
place on the mounting brackets.
Front
Summary of Contents for SPARC ENTERPRISE T1000
Page 1: ......
Page 2: ......
Page 6: ......
Page 10: ...viii SPARC Enterprise T1000 Server Installation Guide April 2007 ...
Page 12: ...x SPARC Enterprise T1000 Server Installation Guide April 2007 ...
Page 13: ...xi Tables TABLE 1 1 Ethernet Connection Transfer Rates 9 TABLE 3 1 Server Device List 38 ...
Page 14: ...xii SPARC Enterprise T1000 Server Installation Guide April 2007 ...
Page 16: ...xiv SPARC Enterprise T1000 Server Installation Guide April 2007 ...
Page 25: ...Preface xxiii Reader s Comment Form ...
Page 36: ...10 SPARC Enterprise T1000 Server Installation Guide April 2007 ...
Page 68: ...42 SPARC Enterprise T1000 Server Installation Guide April 2007 ...
Page 78: ...52 SPARC Enterprise T1000 Server Installation Guide April 2007 ...
Page 82: ...56 SPARC Enterprise T1000 Server Installation Guide April 2007 ...
Page 83: ......
Page 84: ......