4
Compress the spring mounted rail to its length, putting the preloaded screw head in the
lower front lug of the rail from behind into the appropriate hole of the right front rack post
as shown below.
The rail now is positioned between the two rack posts by its spring pressure. Support the rail with one
hand.
Figure 2.9 Setting in the right rail at the front
5
Screw on the upper lug of the front rail end to the right front rack post using one screw with
centering washer as shown below.
Figure 2.10 Screwing on the right rail at the front