Calibration Adjustment
Final Calibration For v11.10 and later
5
5-11
Warming-Up 2, Warm-Up Final, and ADC Timing
The Warming-Up 2 step (
CL 0500
) must be done with open inputs:
1. Press
F3
to start the calibration.
2. Wait until the display shows calibration status
End Precal:READY
.
3. Press
F2
to select the next calibration step (
CL 201, WarmUpFinal
).
4. Press
F3
to start the calibration.
5. Wait until the display shows calibration ready. Press
F2
to select the
next calibration step (
CL 0570, ADC Timing
).
6. Connect Ch. A of the Test Tool to the 5502A SCOPE output as shown in
Figure 5-3. Use a 50
Ω
termination.
7. Set the 5502A to generate a sine wave 50 MHz / 0.5 V pp (mode LEVSINE)
at the SCOPE output.
8. Set the 5502A in operate (OPR).
9. Press
F3
to start the calibration.
10. Wait until the display shows calibration status
:READY.
11. Set the 5502A in standby (STBY).
12. Continue at the
Input A LF-HF Gain
section.
NORMAL
SCOPE
FLUKE 5502A CALIBRATOR
USE 50 OHM
TERMINATION
A
B
METER
TRM 50 - 50 OHM
PM9091
2 CHANN. + METER
For 190-502 and -504
use only TRM50!
perf-ver-d2-500.eps
Figure 5-3. 5502A SCOPE Output to Test Tool Input A