2. Commissioning
2−54
Festo P.BE−CPX−FB38−EN en 0804NH
2.9
Bus node replacement
Procedure
1. Stop the process controller (PLC/Master):
2. If necessary, disconnect the power supply and
compressed air supply.
3. Replace the bus node (Dismantling/Installation:
see section 1.1).
4. Switch the power supply back on.
5. Start your configuration and programming software
(e.g.Beckhoff TwinCAT).
6. Perform a new configuration (hardware and network
configuration).
7. Start the process controller (PLC/Master); choose the
EtherCAT operating status
Pre−operational
(network
configuration).
The controller loads all required EtherCAT data into the
bus node.
8. Recreate the required parameterisation; to do this,
use the CPX−MMI or CPX−FMT.
9. If necessary, switch the compressed air supply back on.
10. Start the program process (PLC/Master); choose the
EtherCAT operating status
Operational
.
TheCPX terminal or your EtherCAT system is again in
normal operating condition.
Summary of Contents for CPX-FB38
Page 2: ......
Page 8: ...Contents and general instructions VI Festo P BE CPX FB38 EN en 0804NH...
Page 17: ...Installation 1 1 Festo P BE CPX FB38 EN en 0804NH Chapter 1...
Page 37: ...Commissioning 2 1 Festo P BE CPX FB38 EN en 0804NH Chapter 2...
Page 91: ...Diagnosis 3 1 Festo P BE CPX FB38 EN en 0804NH Chapter 3...
Page 111: ...Technical appendix A 1 Festo P BE CPX FB38 EN en 0804NH Appendix A...
Page 115: ...Index B 1 Festo P BE CPX FB38 EN en 0804NH Appendix B...
Page 116: ...B Index B 2 Festo P BE CPX FB38 EN en 0804NH Contents B Index B 1...