2. Commissioning
2−50
Festo P.BE−CPX−FB38−EN en 0804NH
2
1
EtherCAT
controller/
Master (IPC...)
EtherCAT
I/O controller
(if necessary CPX−FEC)
3
1
With default parameter set:
The controller or the I/O Controller initiates use of the
factory−programmed
default parameter set; the bus node then distributes the parameter set to the
modules.
2
With saved parameter set:
The CPX bus node distributes the parameter set
saved in the bus node
, which
may have been changed or adapted by means of CPX−MMI or CPX−FMT.
3
With default" parameter set using a CPX−FEC in the remote controller operating
mode (parameterisation from the control program of the FEC):
The CPX−FEC loads the
programmed
start parameter set into the CPX bus node;
the bus node then distributes the parameter set to the modules.
Fig.2/9:
Sequence of start parameterisation during switch−on of a CPX terminal with
bus node CPX−FB38
Summary of Contents for CPX-FB38
Page 2: ......
Page 8: ...Contents and general instructions VI Festo P BE CPX FB38 EN en 0804NH...
Page 17: ...Installation 1 1 Festo P BE CPX FB38 EN en 0804NH Chapter 1...
Page 37: ...Commissioning 2 1 Festo P BE CPX FB38 EN en 0804NH Chapter 2...
Page 91: ...Diagnosis 3 1 Festo P BE CPX FB38 EN en 0804NH Chapter 3...
Page 111: ...Technical appendix A 1 Festo P BE CPX FB38 EN en 0804NH Appendix A...
Page 115: ...Index B 1 Festo P BE CPX FB38 EN en 0804NH Appendix B...
Page 116: ...B Index B 2 Festo P BE CPX FB38 EN en 0804NH Contents B Index B 1...