PRE-OPERATION CHECK-OUT AND TEST
71
SECTION VI
6. PRE-OPERATION CHECKOUT
AND TEST
Warning
The following procedures should be
performed by a properly trained
technician to ensure the equipment is
operating properly.
6.1 Visual
Inspection
1. Fill out the Field Test Data Sheet at
the end of this section to document
the following inspections and tests.
The completed document should be
kept on file for future reference.
2. Verify all connections and fasteners
are tight.
3. Ensure that all installation debris is
removed from the cabinet.
4. Secure all wiring with wire-ties to
provide strain relief and to neatly
manage the wiring.
5. Verify the control board clock LED is
blinking.
6. Verify the charger LED(s) are on for
the appropriate charging state.
6.2 Amplifier and Speaker Pre-
Operation Checkout
1. Refer to Figure 5.4. Measure the DC
voltage between battery 1 (-) and
battery 2 (+). The voltage should be
at least 25VDC. If the voltage is
below 25VDC, verify the red
“charging” LEDs are on lit on the
charger. Allow the batteries time to
charge before continuing with the
tests.
2. Refer to Figure 6.1. Verify the
microphone is plugged into the ¼”
jack in the control module. Turn the
mic volume potentiometer fully
counter clockwise. Press the PTT
button on the mic and announce a
test message i.e.: (“Testing 1,2,3,4,
Testing”). Turn the mic volume knob
clockwise until the desired level is
obtained during the test count.
3. Verify the Audio A, Audio B, ARM,
and PA LEDs on the control and the
green LEDs on each amp light when
the test message is broadcast.
4. Calibrate the Quiet Test function by
pressing switches 2 & 3 on the
controller’s front panel at the same
time.
5. All siren signals should be tested at
this time by momentarily depressing
the appropriate switch on the control
module front panel.
Summary of Contents for Personnel Alerting System
Page 49: ...INSTALLATION 49 Figure 5 2 UVIC Cabinet Dimensional Outline Drawing ...
Page 50: ...INSTALLATION 50 Figure 5 3 UVIC Wiring Diagram ...
Page 51: ...INSTALLATION 51 Figure 5 4 UVIC Battery Connections ...
Page 62: ...INSTALLATION 62 Figure 5 5 Yagi Antenna Installation Example ...
Page 63: ...INSTALLATION 63 Figure 5 6 Omni Antenna Installation Example ...
Page 64: ...INSTALLATION 64 Figure 5 7 Antenna Grounding Example ...
Page 69: ...INSTALLATION 69 Figure 5 10 UVLOC Dimensional Outline ...
Page 70: ...INSTALLATION 70 Figure 5 11 UVIC25SD Field Wiring Diagram ...
Page 83: ...83 Figure 9 1 UVIC Final Assembly and Parts List Page 2 of 2 ...
Page 84: ...UVIC Final Assembly and Parts List 84 Figure 9 2 UVIC25ST Wiring Detail ...