4
QUICK REFERENCE SHEET
FOR INSTALLING FBD UNITS
NOTE:
This guide is for quick reference only. It is not intended to replace important detailed information
contained in this Installation, Operation and Service Manual. Thoroughly read the entire manual
before attempting installation.
Checkpoints
Verify the line voltage is between 215 VAC and 245 VAC.
Adjust the voltage offset to make the line voltage and the voltage on the display
match.
Adjust the CO2 secondary regulator to between 28 and 32 psig.
NOTE:
If this is a low carbonation application, the CO2 secondary regulator should be set to between
17 and 19
psig
and requires special software.
Verify on the unit’s display that the CO2 and syrup pressures are at about 70 psig
static.
Verify the water pressure is about 70 psig static for a SHURfl o pump and between
85 and 90 psig for a Flojet pump.
Adjust the water fl ow rate to 1.5 ounces per second.
Adjust the Brix to between 13.5 and 15.0.
Fill barrels with product.
Press “DEF” and then “RUN” for each barrel. There will be a two (2) minute
delay before the compressor starts. The freeze down will take between 8 to 10
minutes.
See Sections 4 through 6 of this manual for further details on each of these
checkpoints and dispenser installation.
NOTE:
If the unit has been in storage for longer than 90 days, FBD recommends that the rear seals be replaced.
Summary of Contents for FBD562
Page 49: ...49 14 8 LOWER BOARD SCHEMATIC FBD 562 562 ELECTRICAL BOX SCHEMATIC ...
Page 50: ...50 14 9 UPPER BOARD SCHEMATIC FBD 563 563 SCHEMATIC UPPER BOARD ...
Page 51: ...51 14 10 LOWER BOARD SCHEMATIC FBD 563 563 ELECTRICAL BOX SCHEMATIC ...
Page 52: ...52 14 11 UPPER BOARD SCHEMATIC FBD 564 564 SCHEMATIC UPPER BOARD ...
Page 53: ...53 14 12 LOWER BOARD SCHEMATIC FBD 564 564 ELECTRICAL BOX SCHEMATIC LPB1 ...