Mounting
Installation location requirements
Ambient temperature during operation 5°C to 40°C
Air humidity during operation 30% to 75% rel. air humidity
Storage temperature: 0°C to 60°C
Stable wall for installation as the total weight can equal approx. 35 kg.
Near the unit: Mains connection of 230 V N AC for 3 kW and 400 V 3N AC
for 4–6 kW (fixed connection).
Drain outlet below the unit or in close proximity
Water supply line in close proximity Cold water, max. 25°C
Length of insulated steam pipe, max. 5 m to 7 m
All pipelines and connections must be accessible for service.
The room in which the steam generator is installed should be as near to the
steam room as possible so that the pipeline distances are as short as possi-
ble.
Steam room requirements
Floor drain
Air extractor so that temperature control works properly
3.1
Steam generator
The following tasks must be completed in order to mount the steam gener-
ator and connect the lines:
Connecting control lines and the mains cable,
Connecting the cold water supply line,
Mounting the motorised ball valve,