XSR Getting Started Guide 2-1
2
Hardware Installation
Introduction
This chapter provides a checklist to verify your shipment and describes how to install the
following XSR hardware:
•
NIM cards
•
Optional - CompactFlash card
•
Optional - DIMM upgrade
•
Optional - Rack-mounted XSR
•
Connecting cables
Verifying Your Shipment
Before installing your XSR, first check your shipment to ensure that everything you ordered
arrived safely. Open the shipping box(es) and verify that you received the following equipment:
•
XSR chassis with installed hardware including any optional NIM cards (shipped separately).
•
One power supply and one country-specific power cable
•
One console cable
•
Quick Start Guide
Installation Site Suggestions
When determining an installation site for the XSR chassis, follow the guidelines outlined below:
•
For proper cooling, maintain a minimum clearance of 15.2 centimeters (6 inches) behind the
chassis and 5.08 centimeters (2 inches) of clearance on either side of the chassis.
•
If installing the XSR chassis as a free-standing unit on a shelf, ensure that the shelf can support
a minimum weight of approximately 5 1/2 pounds per fully loaded chassis plus the weight of
the connected network cables.
•
For access to the rear of the chassis, allow an area of 48.26 centimeters (19 inches) wide by 61
centimeters (24 inches) deep.
•
If installing the XSR chassis in an equipment rack, ensure that the rack can support and
remain stable with the chassis installed.
Note:
For instructions on installing a balun and grounding shunt/terminal strip on E1 NIM cards only,
refer to Appendix A: Specifications on
page A-1
.