Pipework requirements
Good engineering practice should be followed at all times:
• Correct preparation, welding and finishing techniques
• Correctly sized gaskets
• Correctly aligned flanges and gaskets
• Connecting pipe work should match the internal diameter of the flowmeter. Maximum
pipe diameter mismatch should not exceed:
– 1 mm (0.04 in) for diameters < DN 200 (8")
– 3 mm (0.12 in) for diameters
DN 200 (8")
Further information is provided in ISO Standard 14511.
"
Caution!
New installations should be free of metallic and abrasive particles to prevent damage to the
sensing elements on start-up.
A0005103
Correctly aligned flanges and gaskets
A0005104
A0005105
A0005106
Pipe diameter one is not equal pipe
diameter two
Incorrectly sized gaskets
Incorrectly aligned flanges and gas-
kets