2.
Remove security wire.
3.
Remove screws and top cover of the LME.
4.
Disconnect wire connections from the LME.
5.
Disconnect the grounding cables.
6.
Disconnect conduit connections to the turbine meter.
7.
Remove turbine meter from line. Refer to
Safety precautions using appropriately rated lifting slings
for instructions on lifting the
turbine meter.
9.3.1
Disassemble internal meter housing components - NPS
3 through 24
1.
Remove the downstream shaft nut, simultaneously holding the upstream shaft nut
to prevent the shaft from turning.
Downstream shaft nut removal
Figure 9-1:
Important
The shaft nut can only be reused up to five times. Replace as needed.
2.
Remove the downstream hanger assembly from the shaft.
a. Remove the shaft in the upstream direction to allow the insertion of a pin into
the hole in the downstream hanger hub.
b. Push the shaft back against the pin and tap the shaft lightly to free the
downstream hanger assembly.
Planned maintenance
User manual
73
Summary of Contents for daniel 1500 series
Page 8: ......
Page 12: ...Plan 2 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 64: ...Prepare the turbine meter for use 54 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 66: ...Install 56 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 72: ...Installation procedure 62 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 74: ...Testing 64 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 75: ...Part III Operate Operate User manual 65 ...
Page 76: ...Operate 66 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 80: ...Maintain 70 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 101: ...Decommission the turbine meter User manual 91 ...
Page 102: ...Decommission the turbine meter 92 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 103: ...Decommission the turbine meter User manual 93 ...