2.
Thread the nut into the shaft end and insert the shaft through the upstream hanger
assembly on the inlet side.
3.
Insert the upstream cone to the shaft. The thrust washer should remain in the cone.
Upstream cone installation
Figure 9-9:
4.
Insert the journal bearing in to the rotor assembly.
Journal bearing installation
Figure 9-10:
5.
Install the rotor to the shaft.
Planned maintenance
78
Daniel Series 1500 Liquid Turbine Meter, NPS 3-24
Summary of Contents for daniel 1500 series
Page 8: ......
Page 12: ...Plan 2 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 64: ...Prepare the turbine meter for use 54 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 66: ...Install 56 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 72: ...Installation procedure 62 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 74: ...Testing 64 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 75: ...Part III Operate Operate User manual 65 ...
Page 76: ...Operate 66 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 80: ...Maintain 70 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 101: ...Decommission the turbine meter User manual 91 ...
Page 102: ...Decommission the turbine meter 92 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 103: ...Decommission the turbine meter User manual 93 ...