Installation and commissioning
[22]
First the blue shrink sleeve
and then the black shrink sleeve.
2.
Close the connection.
3.
Move the black shrink sleeve over the closed connection. Plug and socket must be
completely covered by the shrink sleeve.
Ensure that the shrink sleeve evenly overlaps plug and socket.
4.
Use a hot air gun to evenly shrink the sleeve. The required shrinking temperature is
approximately 200°C.
5.
Ensure that the shrunken sleeve touches sensor cable, plug, and socket. It is
important that the shrink sleeve cannot slip from the connection.
6.
Move the blue shrink sleeve evenly over the closed connection already isolated with
the black shrink sleeve.
7.
Use a hot air gun to evenly shrink the blue sleeve. The required shrinking
temperature is approximately 200°C.
5.4
Adjustment of measuring chains at the
machine
5.4.1
General connection
Prerequisites
•
-24 V DC power supply, if the converter is not supplied by a measuring amplifier
such as an A6500-UM.
•
Voltmeter with an accuracy of 1
%
.
Procedure
1.
Connect the converter supply -24 V DC (+24 V to (GND)). See
Power supply and output signal connection
2.
Connect the sensor to the sensor socket. See
3.
Measure the output level at pins OUT and (GND). See
Power supply and output signal connection
5.4.2
Sensors EZ 105x and EZ 108x
1.
Loosen the lock nut of the sensor.
See installation guide of the used sensor for further installation details.
2.
Turn the sensor in the holder until the nominal distance between sensor head and
measuring target is reached, and the connected voltmeter indicates the desired
point on the characteristic curve.
(1)
Only necessary for installation in a hazardous environmental.
Summary of Contents for AMS EZ1000
Page 39: ... 35 6 7 Control drawings ...
Page 40: ... 36 ...