SECTION 4:
OPERATING INSTRUCTIONS
4-12
PORT LF
0008595_REV_E
4.1.6
Leak Detection and Condensation Prevention
EdgeTech’s releases are provided with a 5/16-inch diameter purging port on the bottom (Release End)
end cap. The recommended procedure for preparation of the instruments atmosphere is as follows. The
procedure assumes that the user has a vacuum pump, dry nitrogen gas cylinder and compound
pressure/vacuum gauge all arranged on a manifold setup.
1.
Verifying that all other (other than the purge port) O-ring seals have been cleaned, lubricated and
assembled.
2.
Prepare the Purge Port Plug for installation by cleaning and greasing it, the plug must be ready for
immediate insertion.
3.
Insert a purge port adaptor and draw a -3 PSIG vacuum, do not exceed -5 PSIG.
4.
Close the manifold valve to the instrument and allow the instrument to sit of for 15 minutes.
Check the gauge afterwards and verify that the vacuum did not change. This step is done to detect
gross O-ring problems (either cut or missing).
5.
Open the valve to the instruments purge port and:
a.
Backfill the Housing with dry nitrogen gas, do not 5 PSIG.
b.
Draw a -3 PSIG vacuum on the instrument, do not exceed -5 PSIG.
c.
In humid environments, you should repeat this process up to four times.
d.
After drawing the final vacuum in this process, quickly insert the purging plug before the
-3 PSIG vacuum is lost.
6.
Secure the purge plug with the anti-rotation block and nylon screws.
CAUTION!
When purging the instrument, be careful not to draw more than -5 PSIG
vacuum. Exceeding this figure can damage the batteries and electronic
components, which in turn can result in instrument failure. If a purging
set up is not available, then place a desiccant pack inside the Housing to
help reduce moisture.
Summary of Contents for PORT LF
Page 9: ...ix 6 Fax one invoice packing list and a copy of the airway bill to EdgeTech upon shipment...
Page 18: ......
Page 20: ......
Page 25: ...2 5 Figure 2 2 PORT LF Mechanical Standard 0010815...
Page 26: ...SECTION 2 SPECIFICATIONS 2 6 Figure 2 3 PORT LF DEEP Mechanical 0019564...
Page 46: ......
Page 48: ......
Page 65: ...6 17 Figure 6 24 PORT LF Callout Assembly Drawing Page 1 of 2 0008118...
Page 66: ...MAINTENANCE 6 18 Figure 6 25 PORT LF Callout Assembly Drawing Page 2 of 2 0008118...
Page 69: ......
Page 70: ...REMOTE RELEASE B 2 Appendix Figure B 1 Remote Release 0012120...
Page 71: ...B 3 Appendix Figure B 2 PORT LF Optional Remote Release 0012266...
Page 72: ...B 4 Appendix Figure B 3 PORT LF Optional Remote Release Callout 0007639...
Page 74: ...C 2 Appendix Figure C 1 Optional Tandem Kit Diagram 0017625...
Page 75: ...C 3 Appendix Figure C 2 PORT LF Optional Tandem Kit Callout Diagram 0008237...
Page 76: ......
Page 78: ...D 2 Appendix Figure D 1 PORT LF Optional Strongback Diagram 0017674...
Page 79: ...D 3 Appendix Figure D 2 PORT LF Optional Strongback Kit Callout Diagram 0008166...