Important
•Please make sure that only expert specialised staff is connecting the machine at the water-supply
and installing a pressure regulator.
•To avoid decalcification of the machine a water-softener is recommended. A 8l-water-softener
(art.-nr. 89530) is available in the ECM range of products.
Important
• In case you should go for a direct connection of the machine to the drain system, a hole has to be
drilled in the drip tray. This work can be carried out by expert specialised staff or by ECM
Manufacture service.
• Connect a hose (Ø 10 mm) to the designated connector on the back side of the machine and to a
preinstalled siphoned drain.
5 FIRST
USE
5.1 First use
Read the instruction manual carefully before operating the machine.
Before starting the machine, check if:
•
the steam and hot water valves are closed.
•
the machine is switched off. (Power switch in lower position.)
•
the power cord is disconnected.
•
the drip tray is inserted accurately.
Now you can start up your machine:
1
Machine in use with watertank: Take out the water tank and rinse it thoroughly.
2
Fill the water tank with fresh water deficient in lime and put it back into the water tank guides and close the cup
warmer tray again.
3
Insert the plug in the wall socket. Turn the power switch to “1”. The machine is on now.
4
The green control lamp lights up.
5
The pump begins to operate filling the boiler of the machine with fresh water.
6
As soon as the filling-up of the boiler is finished, no pump noise is hearable anymore; the orange control lamp is
on now. Water tank machines: As soon as the fresh water sinks down to a certain level in the fresh water tank,
the machine is switched off and the signal of the orange control lamp goes out. Now refill fresh water. The
machine heats up automatically.
7
Water tank machines:
As a large amount of water is required for the first filling of the boiler, refill the water tank
with fresh water.
8
Wait until the boiler pressure gauge indicates approx. 1.0-1.25 bar.
9
A manual “boiler ventilation” is not necessary because the MECHANIKA & TECHNIKA PROFI DUE is equipped
with a professional depression valve that ventilates the boiler in the heat-up phase.
10
Move the group lever into the upper position and dispense approx. 250 ml of water. In this way, the heat
exchanger will be filled with water and the circulation of the water in the thermosyphon system begins.
11
Move the group lever into the lower position. Water tank machines:
Refill the water tank.
12
The machine is now ready for use. Put the cups on the cup heater tray in order to preheat them and enjoy your
coffee.
The MECHANIKA & TECHNIKA PROFI DUE has a fuse to prevent the machine from overfilling.
It is possible that the machine does not heat up when using it for the first time or when dispensing big
quantities of water over the hot water valve. In this case please switch the machine off and on.
6 USE OF THE MACHINE
6.1 Preparation of the machine
The switched off machine can be put into operation as follows:
1
Water tank machines: Fill water into the water tank.
2
Turn the machine on (power switch in position “1”).
3
Wait until the pressure gauge indicates approx. 1.0-1.25 bar.
Summary of Contents for Mechanika IV Due
Page 5: ...60...
Page 16: ...59 Notizen Notes Notities...
Page 48: ...MECHANIKA TECHNIKA PROFI DUE 45 1 1 1 1 2 1 1 1 2 1 1 1 1 1 1 1 2 2 1 4 1...
Page 49: ...MECHANIKA TECHNIKA PROFI DUE 46 27 2 2 ECM MECHANIKA TECHNIKA PROFI DUE...
Page 52: ...MECHANIKA TECHNIKA PROFI DUE 49 0 1 1 2 1 1 0 3 4 0 c ECM 10...
Page 55: ...MECHANIKA TECHNIKA PROFI DUE 52 1 5 2 3 4 5 7 30 7 1 7 2...
Page 59: ...MECHANIKA TECHNIKA PROFI DUE 56 11 7 9 7 9 7 9 52 0 1 5 3 5...