4.6
Installing UPS External and Battery Power Wiring
NOTE
The ISBM and UPM sections are shipped with debris shields covering the ventilation grills on top of
the sections (see Figure 4‐4). Do not remove the debris shields until installation is complete. However, remove
the shields before operating the UPS. Once the debris shields are removed, do not place objects on the
ventilation grills.
NOTE
Remove the ISBM section top or bottom conduit landing plate to drill or punch conduit holes (see
Use the procedures in the following paragraphs to connect the external and battery
power wiring.
4.6.1
2-Hole Barrel Lug Terminations for Bus Bar Installation
Paragraphs 4.6.2 and 4.6.3 require connecting input, output, and battery power wiring
using 2-hole barrel lugs. See Figure 4-15 for the hardware sequence when installing
the lugs to the bus bars. Tighten the nut to the torque value listed in Table 3-7.
NOTE
Conical washers are special purpose washers that look similar to flat washers, except for a slight
conical shape. When installing conical washers, the top of the dome should be next to the nut and the base of
the washer should be against a flat surface such as a bus bar, flat washer, or large terminal.
Hex Nut
Conical Washer
Lug
Bus Bar
Flat Washer
Bolt Head
Lug
Flat Washer
Hex Nut
Conical Washer
Lug
Bus Bar
Flat Washer
Bolt Head
Flat Washer
Single Lug Installation
Double Lug Installation
Figure 4‐3. Typical Bus Bar Barrel Lug Mounting
–
Hardware Assembly Sequence