2.2 ERECTING THE UNIT
2.2.1 Erecting the assembly on the
foundation
Foundation
Before installation of the assembly is started, it must be
ascertained whether the floor on the site is flat and level.
If an Eaton Holec foundation-frame is used this must be
made level by means of metal propping material
If the assembly is to be installed without a foundation-
frame, the highest points of the floor must be located. Any
differences in height in the floor must be compensated for
by metal propping material.
Assembling the cubicles
•
Place the first cubicle vertically on the foundation and
fix it in place. If an assembly consists of more than one
cubicle, it will be sufficient to attach each cubicle to the
foundation frame by means of two bolts.
•
Gaskets should be applied in the places indicated in
Figure 2-10.
•
Place the second cubicle next to the first. Place the
cubicles together at the bottom without a space
between them; it is not possible to eliminate play
between the cubicles using linking-bolts.
Figure 2-10: Position of the gasket
•
Fit the second cubicle to the first using ten hexagonal
bolts M8x20. The five bolts at the back should be fitted
via the left cubicle and the five bolts nearest the front
should be fitted via the cubicle on the right.
N
OTE
When a plug-in cubicle is assembled on the left-
hand side of the switchboard. M8 x 20 bolts should
only be fitted in the front side of the cubicle wall
and in the topmost hole, rear side of this wall.
•
The second cubicle can now also be mounted on the
foundation.
The entire switchboard should be assembled in the manner
described above.
Figure 2-11: Mounting of the front plate
Summary of Contents for Holec Capitole 40
Page 2: ...Administrative data Issue number G01 002 Date of issue 30 09 2008...
Page 62: ...Capitole 40 62 1991 901 G01 002 Place the draw out units into position Figure 3 35...
Page 74: ...Capitole 40 74 1991 901 G01 002 Figure 4 1...
Page 76: ...Capitole 40 76 1991 901 G01 002 Figure 4 2...
Page 78: ...Capitole 40 78 1991 901 G01 002 Figure 4 3...
Page 82: ...Capitole 40 82 1991 901 G01 002 Figure 4 5 Figure 4 6...
Page 84: ...Capitole 40 84 1991 901 G01 002 Figure 4 7...
Page 86: ...Capitole 40 86 1991 901 G01 002 Figure 4 8...
Page 88: ...Capitole 40 88 1991 901 G01 002 Figure 4 9...
Page 90: ...Capitole 40 90 1991 901 G01 002 Figure 4 10...
Page 92: ...Capitole 40 92 1991 901 G01 002 Figure 4 11...
Page 94: ...Capitole 40 94 1991 901 G01 002 Figure 4 12...
Page 96: ...Capitole 40 96 1991 901 G01 002 Figure 4 13...
Page 97: ...Capitole 40 1991 901 G01 002 97 APPENDIX 1 EU DECLARATION OF CONFORMITY...
Page 98: ...Capitole 40 98 1991 901 G01 002 APPENDIX 2 KEMA TEST REPORT...
Page 99: ...Capitole 40 1991 901 G01 002 99...
Page 100: ...Capitole 40 100 1991 901 G01 002 APPENDIX 3 LLOYD S CERTIFICATE...
Page 101: ...Capitole 40 1991 901 G01 002 101...