4.7 Installation

In a typical installation (see Figure 11), the generator (2) and util-

ity power connect to the metered ATS (1).  Power from the utility 

or the generator (2) is fed to the main circuit breaker panel from 

the ATS (1). The circuit breaker in the metered ATS is the service 

entrance disconnect for the installation. 
When the utility power fails, the Generator will sense the failure, the 

generator will start, and when sufficient generator voltage is avail-

able, the ATS will switch.  All loads will receive power from the gen-

erator.    When utility power returns, the ATS will switch all power 

back to the utility source and the generator will shut down after its 

defined cooled down period.

Figure 10. Typical Installation of a Residential ATS.

Figure 11.  One Line Diagram of a Typical Installation.

4.7 Generator Transfer Connection

The generator transfer contact connection terminal blocks are locat-

ed beside the contactor near the side of the enclosure. 

ote: 

N

Prior to making the generator transfer connection to the aTS, set the genera-

tor control selector switch to the OFF position to prevent an unwanted generator 

start. Control wiring, such as the generator transfer wires and utility sensing, must 

be run in a separate conduit from the power cables.

Watt-Hour

Meter

Generator

(Source 2)

Utility

(Source 1)

Circuit

Breaker

Main

Breaker

Panel

Household

Loads

Metered Transfer Switch

Circuit

Breaker

Use the proper wire size as listed by the generator set (Genset) 

manufacturer.

Figure 12. Connection of the Generator Transfer Signal (23, 194). 

4.8 Preliminary Checks

After the ATS enclosure is installed and power cables are connected 

to the equipment, thoroughly inspect the unit to ensure that no tools 

were left inside and that the cabinet is free of debris.  If necessary, 

use a vacuum cleaner to remove any and all construction or installa-

tion debris from the equipment.
Read and understand all labels on the equipment.  Review and 

understand the wiring diagrams supplied with the equipment.  Note 

any optional accessories that may have been furnished with this unit 

and review their operation.
Verify that the phase-to-phase line voltages of both the utility and 

generator power sources are the same and that they match the 

rated voltage as indicated on the ATS ratings label.

CaUTiOn

SEVErE EQUiPMEnT DaMagE Can rESULT iF THE UniT iS nOT aPPLiED 

aT PrOPEr VOLTagE.  DO nOT EnErgiZE THE EQUiPMEnT iF THE SUPPLY 

VOLTagES DO nOT MaTCH EQUiPMEnT raTingS LaBEL.

Generator 

Transfer 

Contacts

Summary of Contents for EGS Series

Page 1: ...uipment Description 5 4 Installation and Wiring 8 5 Functional Testing 12 6 Adjustments 13 7 Maintenance and Component Replacement 14 Effective January 2014 Instruction Booklet IB0162063EN O M Manual...

Page 2: ...e proceeding If fur ther information is required by the purchaser regarding a particular installation application or maintenance activity please contact an authorized Eaton sales representative or the...

Page 3: ...ear Conversely if connected to the generator power source and the generator power source fails while the utility power source is still unavailable the ATS remains connected to the generator power sour...

Page 4: ...e when it is within its undervoltage setpoint ranges for the nominal voltage setting Connected Connected is defined as when the input is shorted by an external contact or connection Failed or Fails A...

Page 5: ...site and ready to be installed the packaging material can be removed Refer to Section 4 of this manual for specific installation instructions 2 3 Storage Although well packaged this equipment is not s...

Page 6: ...configuration or an under ground one Twin 2 hub openings on the top of the enclosure will accept a standard Myers type hub The assembly ships with removable hub closure plates installed over these ope...

Page 7: ...e lugs sup plied will accommodate the power cables being used Also verify that the cables comply with all local electrical codes Standard ATS equipment as supplied from the factory will accommodate th...

Page 8: ...range number of Cables per Phase 100 14 1 0 AWG 1 200 4 AWG 300 MCM 1 CaUTiOn iMPrOPEr POWEr CaBLE COnnECTiOnS Can CaUSE EXCESSiVE HEaT anD SUBSEQUEnT EQUiPMEnT FaiLUrE ote N Tighten the cable lugs to...

Page 9: ...ector switch to the OFF position to prevent an unwanted generator start Control wiring such as the generator transfer wires and utility sensing must be run in a separate conduit from the power cables...

Page 10: ...ontactor will automatically switch to the UTILITY position WARNING CONTACT WITH ENERGIZED COMPONENTS WILL CAUSE ELECTRICAL SHOCK CAPABLE OF PRODUCING SEVERE PERSONAL INJURY OR DEATH USE EXTREME CAUTIO...

Page 11: ...DEVICE FAILURE TO FOLLOW THIS PROCEDURE COULD CAUSE SEVERE PERSONAL INJURY AND OR DEATH ALWAYS TURN THE utility POWER OFF AND TURN THE generator IF A GENERATOR CONTROL SELECTOR SWITCH TO THE oFF POSI...

Page 12: ...inspection and or maintenance Disconnect the line power from the equipment being serviced by opening next highest disconnect device Make certain that any accessory control power is switched off b Ins...

Page 13: ...IB0162063EN Effective January 2014 O MManualfortheEGSMetered Service EntranceAutomaticTransferSwitchwithRelayControl Eaton Corporation www eatoncanada ca Figure 15 Wiring Diagram for the EGSC ATS Show...

Page 14: ...B0162063EN Effective January 2014 O MManualfortheEGSMetered Service EntranceAutomaticTransferSwitchwithRelayControl Eaton Corporation www eatoncanada ca 7 3 Maintenance Log Date Action Example 01 01 1...

Page 15: ...DEATH ALWAYS TURN THE UTILITY SOURCE 1 POWER OFF AND TURN THE GENERATOR SOURCE 2 CONTROL SELECTOR SWITCH TO THE OFF POSITION BEFORE ATTEMPTING TO REPLACE ANY COMPONENTS NOTICE Apply utility source 1 p...

Page 16: ...thRelayControl Eaton Corporation www eatoncanada ca Figure 16 Dimensions and Plan View of a Service Entrance EGS in 200A 2 2 Hub Openings 5 90 150mm 5 90 150mm 7 81 198mm 36 19 919mm 29 47 749mm 4 69...

Page 17: ...17 Instruction Booklet IB0162063EN Effective January 2014 O MManualfortheEGSMetered Service EntranceAutomaticTransferSwitchwithRelayControl Eaton Corporation www eatoncanada ca Notes...

Page 18: ...ractual agreement between the parties This literature is not intended to and does not enlarge or add to any such contract The sole source governing the rights and remedies of any purchaser of this equ...

Reviews: