DOCUMENT 1218
REV. B
Instruction Manual
AGS-LED
312 LED Series
300mm and 400mm
7
9.7.
Visual Inspection
WARNING
:
IMPORTANT
Check the sign for shipping damage upon arrival and in all cases.
Check for damage prior to installation.
9.8
Raising the Sign (Part 1)
9.8.1 Signs with Internal Power Cable Method 1
a.
Lower the sign with the legs and flanges into place on the anchor studs, see
Figure 37
pg. 63
. Do not yet install the ½” flange nuts.
b.
Plug the sign power cable plug into the secondary receptacle inside the conduit elbow,
protruding through the base plate, while lowering, see
Figure 37, pg. 63
. Do not apply
heat shrink tubing or tape to this connection. The power plug is designed to disconnect
during a frangible event.
c.
Apply Loctite 8023 marine grade anti-seize to the exposed anchor stud threads.
d.
Place one ½” two-piece lock washer and one ½” flange nut onto each anchor stud.
e.
Tighten the flange nuts finger tight.
f.
Follow the instructions of
Section 9.9
to finish raising the sign.
9.8.2
Signs with Internal Power Cable Method 2
a.
Remove the frangible legs from the sign’s leg connectors by unfastening the set screws.
b.
Lower the floor flanges, with legs attached, onto the sign anchor studs. Do not yet
install the ½” flange nuts.
c.
Lower the sign onto the frangible legs, inserting the sign power cable into the power
leg.
d.
Fasten and torque the M5 set screws into the leg connector, see
Table 18, pg 91
, for
torque values.
e.
Plug the sign power cable into the secondary receptacle inside the conduit elbow,
protruding through the base plate, see
Figure 36, pg. 62
. Note, Do not apply heat