UPS Installation Plan and Unpacking
3-18
Eaton
®
Power Xpert
®
9395C UPS Installation and Operation Manual
P-164000821—Rev 01
www.eaton.com/powerquality
CAUTION
Do not tilt the UPS cabinets more than 10° from vertical or the cabinets may tip over.
ATTENTION!
Ne pas incliner les armoires d’onduleur à plus de 10 degrés de la verticale puisqu’elles pourraient
se renverser.
3.
Set the pallet on a firm, level surface, allowing a minimum clearance of 3m (10 ft) on each side for
removing the cabinet from the pallet.
4.
Remove the protective covering from the cabinets.
5.
Remove the packing material, and discard or recycle in a responsible manner.
6.
Inspect the contents for any evidence of physical damage, and compare each item with the Bill of Lading.
If damage has occurred or shortages are evident, contact an Eaton service representative immediately to
determine the extent of the damage and its impact on further installation.
NOTE
The ISBM and PM sections are shipped with debris shields covering the ventilation
grills on top of the sections (see Figure 4-13). Do not remove the debris shields until
installation is complete.
NOTE
While waiting for installation, protect the unpacked cabinets from moisture, dust,
and other harmful contaminants. Failure to store and protect the UPS properly may
void your warranty.
Summary of Contents for 9395C-1000/1000
Page 2: ......
Page 23: ...Section I Installation ...
Page 24: ......
Page 93: ...Section II Operation ...
Page 94: ......
Page 155: ......
Page 156: ... P 164000821 1 P 164000821 1 ...