DSE Model 7560 ATS and Mains Controller Operators Manual
057-017 7560 OPERATING MANUAL ISSUE 10.2 10/02/09 AM 31
6.1 MANUAL OPERATION
Operation
Detail
To initiate a start sequence, press the ‘Manual’
push-button.
The LED above the manual button will illuminate
and the LCD display will then indicate:
Status
Mains on load
Manual mode
Then, press the START push-button. The 7560
will issue a start command to all connected 7510
controllers.
NOTE:- If running on load demand option is set to “Start sets sequentially” then one set
will start at a time as load levels rise.
If configured to “start all sets initially” then all sets will start at the same time.
The 7560 will display:
Any available 7510 in auto mode will be issued with a start
signal.
Please refer to the 7510 operating manual for further details of
the start sequence
Status
Start request
Manual mode
Once the Minimum number of sets (set using 75xx software)
have synchronised onto the bus, the 7560 will display:
Status
Mains on load
Manual mode
Pressing the transfer to bus/open mains button
will
synchronise the bus to the mains. The 7560 will display:
Status
Synchronise bus
Manual mode
Once the bus has synchronised to the mains, the bus will close
and power will be ramped onto the bus (generators). The 7560
will display:
Status
Ramp onto bus
10% kW 12% kVAr
Manual mode
Once the bus power / mains power level has been reached
(configured using 75xx software) the 7560 will display:
Status
Continuous paralleling
Manual Mode
The system will remain in this mode until further action is taken.
Pressing the transfer to bus/open mains button
again will
transfer the remaining load onto the bus (generators). The 7560
will display:
Status
Ramp onto bus
10% kW 12% kVAr
Manual mode
Once the mains loading has reached 0 kW the mains will open
and the 7560 will display:
Status
Bus on load
Manual mode