Page | 16
Dryer Master DM510
Installation Manual
Installation Checklist
The following checklist will help to ensure all steps in the installation process are covered. Once you
have completed all the items on this checklist you can move on to Commissioning the DM510. There
is a dedicated DM510 Commissioning Manual (included with the manual package) to guide you
through the process, but as always you can call the Dryer Master Support Center with any questions.
There are some portions of the Commissioning process that can be handled more easily over the
phone, so do not hesitate to call us.
DM510 Control Panel
The DM510 control panel is mounted in a “NON HAZARDOUS” environment. The ambient
temperature during operation should be maintained between 40° and 105°F (5° to 41°C). The
system can function outside of these limits but it may impact product longevity. The system requires
an 110VAC or 220VAC 50-60HZ grounded circuit. A circuit with isolated ground in conjunction with
approved surge protection equipment will afford extra surge and lightning protection. Surge
protection and/or a UPS if power is unstable may be of benefit.
The DM510 control panel is to be located in the control room from where the operators currently
control operations. For viewing ease it is recommended that the DM510 control panel be mounted
so that the bottom of its display screen is at or slightly above average eye level.
Meets environmental requirements
Meets electrical requirements
Panel installed as described in a NON HAZARDOUS environment
Dryer Master I/O system
The Dryer Master I/O system can be left in the DM510 panel or it can be separately mounted in a
“NON HAZARDOUS” environment. The
I/O board can be installed in the dryer control panel or an
electrical enclosure in close proximity to the dryer control panel. The I/O system will function
throughout the standard industrial temperature range of 0° to 140°F (-20° to 60°C). The I/O system
is powered from the DM510 panel and requires no external power source.
Meets environmental requirements
Panel installed as described in a NON HAZARDOUS environment
For the wireless I/O option only, plug in the supplied power supply to power the
. wireless modem and the Dryer Master I/O
Summary of Contents for DM510
Page 1: ...INSTALLATION GUIDE ...