Situation 2 Overview: Retrofit onto an existing dryer
DMSI Responsibilities:
•
To ship the equipment to site
•
To provide over the phone assistance during the installation process and during the system
start-up
•
To assist the site operator(s) by phone during the drying season
Site Responsibilities (please see enclosed checklist and the installation manual for
more detailed information):
•
To mount the inlet moisture sensor, the outlet moisture sensor, the drying air temperature
sensor (or temperature signal converter), the sample button, and Dryer Master I/O system (if
not retained in the DM510 cabinet)
•
To mount the DM510 panel
•
To install conduit and run wiring from the DM510 panel to the Dryer Master I/O system (If
applicable)
•
To install conduit and run wiring from the field devices to the Dryer Master I/O system
•
To terminate connections at the field devices, the Dryer Master I/O system (if so equipped)
and at the DM510 panel
•
To start-up the system with over the phone assistance from the Dryer Master Support
Centre
•
To arrange an over the phone commissioning time with the Dryer Master Support Centre