Dryer Master DM510
Installation Manual
The cables required between the DM510 and I/O panel are 2 Multi-cables. One for communications,
one for a spare and a minimum 16-gauge green ground wire from the DM510 chassis ground to the
DM510 I/O Panel chassis ground.
The communication cable is created by removing the connections from the cable present in the
DM510, noting the positions. Note the location of the individual conductors (see Figure 19 - I/O
assembly removal) Remove the end connectors. Cut two Multi-cables that are long enough to reach
between the DM510 and the location of the I/O panel. One will replace the current cable and the
second will be a spare. Mark them to identify them from each other. Pull these cables along with a
16 awg. Green ground wire into the conduit between the DM510 and the I/O panel. Rewire the end
connectors as noted below and connect them to the noted location as they were connected in the
original configuration. See Figure 23
–
Communications Wire Layout for details.
Conduit required to house the cables between the DM510 and the I/O
panel is ½”. The wire entry
points in the bottom of the DM510 are sized for a ¾ “ conduit.
Figure 20 - Communications Wire Layout