5.6
Start-up
In order for the
warranty to be valid
, the module must be started up by an official
DOMUSA
TEKNIK Technical Assistance Service
. Before beginning the start-up process, the following must be
complied with:
- The module and the DUAL CLIMA heat pump should be electrically connected to the network.
- The installation should be filled with water (the pressure should be between 0.1 to 0.15 MPa
(1 to 1.5 bar).
- The fuel should reach the burner at a pressure of no more than 0,05 MPa (0.5 bar).
- Check that the flue is correctly installed.
- If the installation has flow and return valves, check that they are open.
- If there is a room thermostat, adjust it to the desired temperature.
- It is essential to carry out a combustion analysis of the module, using a suitable analyser for
this purpose. If the combustion analysis is not correct, the burner must be adjusted until it is
corrected.
To start the module, follow the instructions in the
“Operation”
section.
Summary of Contents for Fusion Hybrid Oil
Page 1: ...INSTALLATION AND OPERATING INSTRUCTIONS FUSION HYBRID OIL MODULE ...
Page 31: ...29 12 5 Load losses ...
Page 45: ...43 FUSION HYBRID OIL Plumbing ...
Page 49: ...47 NOTES ...
Page 50: ...Fusion Hybrid Oil 48 NOTES ...
Page 51: ...49 NOTES ...