![Ditch Witch JT1220 Mach 1 Operator'S Manual Download Page 140](http://html1.mh-extra.com/html/ditch-witch/jt1220-mach-1/jt1220-mach-1_operators-manual_2510007140.webp)
JT1220 Mach 1 Operator’s Manual
Systems and Equipment - 139
Pipeloader
CMW
Remove Single Pipe
Unload all drill pipe loaded with auxiliary pipe loaders.
1.
Lift, rotate, and lock pipe positioning aid (3) into
stowed position.
2.
Ensure pipe box is positioned properly. See “Shift
Pipe Box” on page 135.
3.
Move shuttles out fully.
4.
Pull pin (2) on shuttle, rotate auxiliary pipe loader
(1) down, and install pin.
5.
Repeat process for other shuttle.
6.
Raise pipe.
7.
Move pipe to auxiliary pipe loaders.
•
Move shuttles in.
•
Lower pipe into auxiliary pipe loaders.
8.
Move shuttles out.
9.
Remove pipe from auxiliary pipe loaders and store properly.
10. Repeat steps 5-8 to unload remaining added drill pipe.
11. After all added drill pipe is unloaded with auxiliary pipe loaders:
•
Close both auxiliary pipe loaders.
•
Step away from pipeloader.
•
Finish loading remaining drill pipe using standard procedure. See “Remove Pipe” on page 103.
Crushing weight. If load falls or moves it could kill or crush you.
Use proper procedures and equipment or stay away.
Summary of Contents for JT1220 Mach 1
Page 1: ...JT1220 Mach 1 Issue 2 1 Operator s Manual 054 114 CMW...
Page 19: ...Safety 18 JT1220 Mach 1 Operator s Manual Emergency Procedures CMW...
Page 75: ...Prepare 74 JT1220 Mach 1 Operator s Manual Check Supplies and Prepare Equipment CMW...
Page 107: ...Conduct a Bore 106 JT1220 Mach 1 Operator s Manual Remove Pullback Device CMW...