3
Figure 1 : Mounting configurations
1.5)
CLEARANCES
The following clearances should be provided for the servicing of the
unit:
Table 1
Minimum clearances to combustible materials
LOCATION
CLEARANCE
Access side to elements
13 ¼‘’ (34 cm)
Sides
4’’ (10 cm)
Bottom (water connections)
6 5/8’’ (17 cm)
Front*
0
Back
0
* If the boiler is in an enclosure, provide a door or a removable panel
in front to access the control panel.
1.6)
DISTRIBUTION SYSTEM
The proper functioning of your heating system is directly related to
the quality of the plumbing installation. Therefore, the entire
installation must be performed by qualified technicians.
See Figure 2 for the functions of the various boiler components.
The heating system must be set-up to operate at a maximum
pressure of 28 psi and the operating temperature may range from
21
o
C to 88
o
C (70
o
F to 190
o
F).
Summary of Contents for HYDRA COMPACT HYDRAC03-M2401M
Page 9: ...9 Figure 6 Diagramme multizone avec valves motoris es Figure 7 Diagramme lectrique...
Page 10: ...10 SECTION 6 PI CES DE REMPLACEMENT Figure 8 Vue explos e...
Page 12: ......
Page 21: ...9 Figure 6 Multizone diagram with Motorized Valves Figure 7 Electrical Diagram...
Page 22: ...10 SECTION 6 REMPLACEMENT PARTS Figure 8 Exploded Vue...
Page 24: ......