PQRM5300 33 Ux Ix xx xx (PS)
16
20201120-V1
5.2. Connecting the measuring inputs to power network.
Three phase measurement with neutral conductor. (3
phase, 4 wire, 3 measuring)
The following figure shows the wiring plan, connecting the
instrument to low voltage power network with neutral
conductor.
Wiring plan, connecting
the voltage and current
inputs to power network.
The terminal “k” of CT you
have to connecting to
earth!
1. Loosen terminal screws.
2. Insert the wire ends into the open terminals according to
the wiring plan.
3. Screw the terminal in.
4. Check the hold of the wires in terminals by pulling on
them firmly.
Checking the
connections
Check if the cables are connected properly (have you
connected all the cables, have you connected to the right
place, do not the cable-ends touch each other).