7 Commissioning

Installation and operation manual

21

5TMV1B
VRV IV-S system air conditioner
4P399985-1B – 2015.06

Damaged equipment

Check  the  inside  of  the  unit  on  damaged  components  or
squeezed pipes.

Refrigerant leak

Check the inside of the unit on refrigerant leakage. If there
is  a  refrigerant  leak,  try  to  repair  the  leak.  If  the  repair  is
unsuccessful,  call  your  local  dealer.  Do  not  touch  any
refrigerant  which  has  leaked  out  from  refrigerant  piping
connections. This may result in frostbite.

Oil leak

Check  the  compressor  for  oil  leakage.  If  there  is  an  oil
leak, try to repair the leak. If the repairing is unsuccessful,
call your local dealer.

Air inlet/outlet

Check  that  the  air  inlet  and  outlet  of  the  unit  is  not
obstructed  by  paper  sheets,  cardboard,  or  any  other
material.

Additional refrigerant charge

The amount of refrigerant to be added to the unit shall be
written  on  the  included  "Added  refrigerant"  plate  and
attached to the rear side of the front cover.

Installation date and field setting

Be  sure  to  keep  record  of  the  installation  date  on  the
sticker  on  the  rear  of  the  front  panel  according  to
EN60335‑2‑40 and keep record of the contents of the field
setting(s).

7.3

Checklist during commissioning

To perform a 

test run

.

7.3.1

About test run

The  procedure  below  describes  the  test  operation  of  the  complete
system. This operation checks and judges following items:

▪ Check of wrong wiring (communication check with indoor units).

▪ Check of the stop valves opening.

▪ Judgement of piping length.

Make  sure  to  carry  out  the  system  test  operation  after  the  first
installation. Otherwise, the malfunction code 

 will be displayed on

the user interface and normal operation or individual indoor unit test
run cannot be carried out.

Abnormalities  on  indoor  units  cannot  be  checked  for  each  unit
separately. After the test operation is finished, check the indoor units
one  by  one  by  performing  a  normal  operation  using  the  user
interface. Refer to the indoor unit installation manual for more details
concerning the individual test run.

INFORMATION

▪ It may take 10 minutes to achieve a uniform refrigerant

state before the compressor starts.

▪ During the test operation, the refrigerant running sound

or the magnetic sound of a solenoid valve may become
loud and the display indication may change. These are
not malfunctions.

7.3.2

To perform a test run (7-LEDs display)

1

Make  sure  all  field  settings  you  want  are  set;  see 

"6.1  Making

field settings" on page 15

.

2

Turn  ON  the  power  to  the  outdoor  unit  and  the  connected
indoor units.

NOTICE

Be  sure  to  turn  on  the  power  6  hours  before  operation  in
order  to  have  power  running  to  the  crankcase  heater  and
to protect the compressor.

3

Make  sure  the  default  (idle)  situation  is  existing  (H1P  is  OFF);
see 

"6.1.4 To access mode 1 or 2" on page 16

. Push BS4 for 5

seconds or more. The unit will start test operation.

Result: 

The  test  operation  is  automatically  carried  out,  the

outdoor  unit  H2P  flashes  and  the  indication  "Test  operation"
and "Under centralised control" will display on the user interface
of indoor units.

Steps during the automatic system test run procedure:

Step

Description

Control before start up (pressure
equalisation)

Cooling start up control

Cooling stable condition

Communication check

Stop valve check

Pipe length check

Pump down operation

Unit stop

INFORMATION

During the test operation, it is not possible to stop the unit
operation  from  a  user  interface.  To  abort  the  operation,
press BS3. The unit will stop after ±30 seconds.

4

Check  the  test  operation  results  on  the  outdoor  unit  7‑LEDs
display.

Completion

Description

Normal
completion

Abnormal
completion

Refer to 

"7.3.3 Correcting after abnormal

completion of the test run" on page 21

 to take

actions for correcting the abnormality. When
the test operation is fully completed, normal
operation will be possible after 5 minutes.

7.3.3

Correcting after abnormal completion of
the test run

The test operation is only completed if there is no malfunction code
displayed.  In  case  of  a  displayed  malfunction  code,  perform
correcting actions as explained in the malfunction code table. Carry
out  the  test  operation  again  and  confirm  that  the  abnormality  is
properly corrected.

INFORMATION

If a malfunction occurs, the error code is displayed on the
user interface of the indoor unit.

INFORMATION

Refer to the installation manual of the indoor unit for other
detailed malfunction codes related to indoor units.

7.3.4

Operating the unit

Once  the  unit  is  installed  and  test  operation  of  outdoor  unit  and
indoor units is finished, the operation of the system can start.

For  operating  the  indoor  unit,  the  user  interface  of  the  indoor  unit
should be switched ON. Refer to the indoor unit operation manual for
more details.

Summary of Contents for RXYSCQ4TMV1B

Page 1: ...Installation and operation manual VRV IV S system air conditioner English Installation and operation manual VRV IV S system air conditioner RXYSCQ4TMV1B RXYSCQ5TMV1B...

Page 2: ...A B C 250 300 1000 A B C E 250 300 1000 1000 500 D 1000 D E 1000 1000 500 B D HD HU 300 1000 HD HU 250 1500 HU HD HU 300 1500 B D E HB HD HB HU 300 1000 1000 500 HU HB HU 300 1250 1000 500 HB HU HB H...

Page 3: ...sete dokumentidega kui neid kasutatakse vastavalt meie juhenditele atitinka emiau nurodytus standartus ir arba kitus norminius dokumentus su s lyga kad yra naudojami pagal m s nurodymus tad ja lietoti...

Page 4: ...settings 15 6 1 1 About making field settings 15 6 1 2 To access the field setting components 16 6 1 3 Field setting components 16 6 1 4 To access mode 1 or 2 16 6 1 5 To use mode 1 16 6 1 6 To use m...

Page 5: ...nit Outdoor unit installation and operation manual Installation and operation instructions Installer and user reference guide Preparation of the installation technical specifications reference data De...

Page 6: ...eep the drain holes of the unit free by using proper equipment In heating T AO C WB a b 20 15 5 15 10 5 0 5 10 15 20 10 15 20 2527 30 TAI C DB a Warming up operation range b Operation range TAI Ambien...

Page 7: ...r the change over from inch to mm pipes field supply The additional refrigerant calculation has to be adjusted as mentioned in 5 6 2 To determine the additional refrigerant amount on page 12 A Piping...

Page 8: ...wer supply must be protected with the required safety devices i e a main switch a slow blow fuse on each phase and an earth leakage protector in accordance with the applicable legislation Selection an...

Page 9: ...es dimensions in mm 52 102 118 59 62 216 130 20 98 21 89 32 a a Drain holes 5 2 4 To prevent the outdoor unit from falling over Connect cables field supply as shown 4 5 3 Connecting the refrigerant pi...

Page 10: ...the service cover and the piping intake plate 6 Seal all gaps example a to prevent snow and small animals from entering the system a WARNING Provide adequate measures to prevent that the unit can be u...

Page 11: ...be leak and vacuum tested Keep any possible field supplied field piping valves open as well Refer to the indoor unit installation manual for more details Leak test and vacuum drying should be done be...

Page 12: ...shed in a correct way between outdoor unit s and indoor units NOTICE Before starting charging procedures check if the 7 LEDs display is as normal see 6 1 4 To access mode 1 or 2 on page 16 and there i...

Page 13: ...valves At this point valve A must remain closed 7 Take all the precautions mentioned in 6 Configuration on page 15 and 7 Commissioning on page 20 into account 8 Turn on the power of the indoor units...

Page 14: ...to prevent rusting When passing electrical wiring through the knockout holes wrap the wiring with protective tape to prevent damage b c a a Knockout hole b Burr c Sealant etc 5 7 3 Guidelines when co...

Page 15: ...ed as applicable DANGER RISK OF ELECTROCUTION 6 1 Making field settings 6 1 1 About making field settings To configure the heat pump system you must give input to the outdoor unit s main PCB A1P This...

Page 16: ...ON the display goes to its default situation From there you can access mode 1 and mode 2 Initialisation default situation NOTICE Be sure to turn on the power 6 hours before operation in order to have...

Page 17: ...he unit compared to nominal operating conditions Low noise operation can be set in mode 2 There are two methods to activate low noise operation of the outdoor unit system The first method is to enable...

Page 18: ...uto 46 C 43 C 2 12 Enable the low noise function and or power consumption limitation via external control adaptor DTA104A61 62 If the system needs to be running under low noise operation or under powe...

Page 19: ...efault Level 2 Level 3 2 26 Low noise operation start time This setting is used in conjunction with setting 2 22 20h00 default 22h00 24h00 2 27 Low noise operation stop time This setting is used in co...

Page 20: ...s Once all below checks are fulfilled the unit must be closed only then can the unit be powered up You read the complete installation and operation instructions as described in the installer and user...

Page 21: ...ud and the display indication may change These are not malfunctions 7 3 2 To perform a test run 7 LEDs display 1 Make sure all field settings you want are set see 6 1 Making field settings on page 15...

Page 22: ...correctly Recalculate the required amount of refrigerant from the piping length and add an adequate amount of refrigerant Refrigerant overcharge Recalculate the required amount of refrigerant from th...

Page 23: ...the side is not possible Single unit Single row of units See figure 1 on the inside of the front cover A B C D Obstacles walls baffle plates E Obstacle roof a b c d e Minimum service space between the...

Page 24: ...pipe S1NPH High pressure sensor S1NPL Low pressure sensor S1PH High pressure switch Y1E Electronic expansion valve main Y3E Electronic expansion valve subcool heat exchanger Y1S Solenoid valve 4 way v...

Page 25: ...expansion valve main Y3E Electronic expansion valve subcool heat exchanger Y1S Solenoid valve 4 way valve Z1C Z7C Noise filter ferrite core Z1F Z5F Noise filter For the user 10 About the system The in...

Page 26: ...1 minute after the heating operation stops The air flow rate may adjust itself depending on the room temperature or the fan may stop immediately This is not a malfunction 12 2 3 About the heating ope...

Page 27: ...ect expansion DX indoor unit d User interface dedicated depending on indoor unit type e BP box required to connect Residential Air RA or Sky Air SA direct expansion DX indoor units f Residential Air R...

Page 28: ...and details of the defect WARNING Do not modify disassemble remove reinstall or repair the unit yourself as incorrect dismantling or installation may cause an electric shock or fire Contact your deal...

Page 29: ...ir thermistor malfunction indoor Movement detector or floor temperature sensor malfunction indoor User interface thermistor malfunction indoor PCB malfunction outdoor High pressure switch was activate...

Page 30: ...or U5 and stops but then restarts after a few minutes This is because the user interface is intercepting noise from electric appliances other than the air conditioner The noise prevents communication...

Page 31: ...tem When another unit is running some refrigerant will still flow through the unit 15 Relocation Contact your dealer for removing and reinstalling the total unit Moving units requires technical expert...

Page 32: ...4P399985 1 B 0000000E 4P399985 1B 2015 06 Copyright 2015 Daikin...

Reviews: