Commissioning Manual EM11A021
DCM601A51 intelligent Touch Manager
5
2. Engineering
2-1 Engineering Workflow
Various engineering works are necessary for using the iTM.
Engineering works can be roughly divided into those carried out at the office in advance and those
carried out on site after installation.
The following diagram shows the engineering workflow.
New installation (Without using the pre-engineering tool)
At the office
See:
Prepare various information.
Check the equipment to connect to DIII-NET.
Allocate the Group Address.
Acquire the upgrade data.
4-8 Upgrade
Acquiring the Activation key
* When necessary
5-1 Activation
Acquiring the Activation key
At the site
Install the iTM.
Installation Manual (EM11A016)
Install the upgrade data.
4-10 Installation
Make basic settings.
(Boot sequence)
Installation Manual (EM11A016)
Set up “Main” and “Sub”.
4-3 DIII-NET Engineering
Activate optional maker functions.
Enable dealer options.
* When necessary
5-1 Activation
Entering the Activation key
5-2 Dealer Option Setup
Register management points and Layout View.
(Load from CSV or register manually)
4-1 Mgmt. Point Data Regist
Summary of Contents for DCM601A51
Page 125: ...EM11A021 1208 HT...