S A F E T Y I N F O R M A T I O N
Attach Facility Lock-Out Tag-Out Device
1-14
Bravo™ 8105 Preventive Maintenance Guide
Rev. 2
1
Attach Facility Lock-Out Tag-Out Device
Introduction
Refer to the following procedure to isolate and identify all facility energy sources.
As soon as all energy sources are isolated and turned to the Off or Stop position,
notify affected personnel and attach the lock-out tag-out device. When all tasks
are complete, the person who attached the lock-out tag-out device is responsible
to notify affected personnel and remove the device.
Safety
To ensure personal safety and avoid equipment damage, observe the following:
Electrical Hazard
Electrical current used can kill. DO NOT TOUCH live electrical components inside
the electrical enclosure. These procedures must be performed only by an
authorized electrician, electrical engineer, or service technician familiar with
testing live voltage.
ATTENTION
If procedures must continue past the shift of the person who applied the lockout
device, ensure that an employee who is working the next shift applies their
lockout device and the previous person removes the initial lockout device.
Procedure
Refer to the following steps to lock-out and tag-out facility power to the Bravo™:
1. Ensure there are no boards or other product in the system.
2. Notify all affected employees.
3. Locate and identify all facility energy sources used, potential hazards, and all
control devices.
4. Turn Off all operating controls.
5. Locate the facility main power input to the system.
6. Turn the facility main power input device to the Off or Stop position.
7. Secure the facility main power lock-out device in place.
8. Test operating controls. Put all controls in the On position. Be sure no one can
get hurt before testing.
9. Return all operating controls to the Off position before proceeding.